Instant calculation, simulation or process mining?

Advanced 9 min read · Updated November 14, 2026

Instant calculation turns the estimates of the people involved into lead time, cost and utilization, deterministically and with a traceable calculation path. Simulation sends individual cases through the process with limited staff and shows how queues build up. Process mining reconstructs the real process from event logs of IT systems and needs data that often does not exist yet. They answer different questions and complement each other.

Instant calculation: typical times, average visits

The app recalculates with every change. For each case type it solves how often each step is passed on average, then adds up the typical processing and waiting times, costs, handoffs and media breaks and compares the work per lane with its capacity (see branches and loops). The result is the same every time for the same input, and every number can be traced back to the steps.

In the worked example “Invoice check” this gives a lead time of 1,229.5 minutes, cost of €17.04 per case and 101% utilization in accounts payable, immediately and without any setup.

The limitation is honest to name: waiting times are an input. If a team is overloaded, the instant calculation shows utilization above 100% and a growing backlog, but it does not make the waiting times longer by itself. The app therefore marks the lead time “only without backlog” as soon as a lane is above 100%: it is then a minimum.

Typical value and mean of the range

The instant calculation uses the typical value of every step, the time it usually takes. That is the figure people name in the interview and recognize in the result; the shortest and longest times go into the lead time range.

When a range is not even around the typical value, because a few cases take much longer, its mean lies above it. Over many cases, this is the work that actually arises on average. For staffing, utilization and annual cost the mean is therefore the more cautious figure. Like the simulation, the app takes a triangle of shortest, typical and longest time. If the result differs noticeably, the figure “with mean of the ranges” appears as a second figure next to utilization, staffing and cost. The simulation with variation works with the same means, which is why it can find a different bottleneck than the instant calculation.

An example with an assumed range: in the worked example “Invoice check”, “Enter invoice” usually takes 6 minutes, at least 4 and at most 14. The mean is (4 + 6 + 14) ÷ 3 = 8 minutes. With the typical value accounts payable needs 266.7 hours a month, with the mean 300 hours. With 264 hours of capacity that is 101% instead of 114% utilization, a backlog of 10 against 120 invoices a month and 1.82 instead of 2.05 FTE. Cost per case rises from €17.04 to €18.88. The typical time describes the normal case, the mean the load across all cases.

Mean of the range = (shortest + typical + longest time) ÷ 3

Simulation: cases through limited capacity

A discrete-event simulation creates individual cases over a period, lets each one draw its case type and path, and has each lane work through its queue with the people available. Cases a lane has already worked on go before new ones, with the same assumption “work in progress first” as the backlog of the instant calculation. Waiting from overload is then a result, not an input.

The app contains such a simulation in its analysis area. You set the simulated period in working days, the number of replications and whether cases arrive evenly or randomly. Processing times vary within the range you entered (best, typical, worst), as a triangular distribution. You can leave out the waiting times from the input to see how much waiting comes from utilization alone. The results include mean lead time, queues and utilization per lane compared with the instant calculation, open cases at the end, and what-if variants such as one more person per lane, halved query rates or each measure on its own. A variant is only called “better” or “worse” if the difference is larger than the spread between the replications; otherwise it reads “not distinguishable with these runs”; if the difference is above the minimum size, more runs can decide. If a relief such as one more person certainly shows more open cases, it is called “measurably opposite”. That is not random fluctuation but a consequence of counting open cases rather than the work in them; Staffing and utilization explains how this comes about.

Process mining: the real process from system data

Process mining reads event logs, for example “order created”, “order released”, “invoice posted” with time stamps, and reconstructs which paths the cases really took and how long they waited. Nothing is estimated; everything that happened in the system is visible.

The precondition is data: the steps must happen in IT systems that write usable logs, with a common case identifier. Work on paper, in email or in conversations leaves no log. Before an ERP implementation, when exactly these parts are to be replaced, there is usually little to mine.

Comparison

AspectInstant calculationSimulationProcess mining
InputEstimates from interviewsSame estimates plus period and arrivalsEvent logs from IT systems
Effort to first numberMinutes after mappingA run after mappingData extraction and preparation
Waiting from overloadInput, overload shown as utilizationResultMeasured
ResultTypical values with average visits, deterministicDistribution over replicationsActual paths and times
Paper and email stepsYesYesOnly if logged

When to use what

Estimates are not a weakness to hide

Estimated times limit the precision of every metric. Ranges make that visible: the app calculates lead time for best, typical and worst case. A rough figure that is available in a workshop is often enough to decide which measure to pursue. Where the decision depends on precision, measure that particular step, or check it later with system data once it exists.

Invoice check (worked example)Invoice check (worked example), drawn from the model the app calculates with, in the same rendering as the export: processing and waiting time per step, “×” top right on steps that run more or less than once per case, the bottleneck step marked in red. The legend below the diagram explains the other symbols. Accounts payable 2 ppl. · 101% Division management 2 ppl. · 84% Supplier Invoice check (worked example) Invoice received ERP Enter invoice 6 min 1 h BOTTLENECK ×1.25 ERP Check invoice 4 min 0 min Complete? Query to supplier 5 working days Amount above €5,000? ×0.3 Approve invoice 5 min 3 working days ERP Post invoice 5 min 2 h Invoice posted yes · 80% no · 20% yes · 30% no · 70% Line width = number of cases Rework loop Bottleneck Lane utilized over 100% Media break worked in an IT system done manually ×0.3 Passes per case, if not exactly one (below 1: only some of the cases) Problem Measure
Invoice check (worked example), drawn from the model the app calculates with, in the same rendering as the export: processing and waiting time per step, “×” top right on steps that run more or less than once per case, the bottleneck step marked in red. The legend below the diagram explains the other symbols.

Try it in the editor

Invoice check (worked example) · 1,000 / month

The worked example has accounts payable at 101% utilization, so the instant calculation shows a backlog of 10 invoices a month that you can compare with a simulation run.

Open the example in the editor

Free, no sign-up, in your browser. Lead time, cost and utilization are calculated while you draw.

Frequently asked questions

Why does the simulation show a longer lead time than the instant calculation?

Two reasons: waiting from overload is added, and when a range reaches further towards the worst case than towards the best case, the average of the triangular distribution lies above the typical value. With unlimited capacity and no variation, both agree.

Do I need process mining for a process analysis?

No. Mining needs system logs. For processes with paper, email or conversations, or before a new system is introduced, mapping with estimates is usually the only source.

How exact is a calculation from estimates?

As exact as the estimates. Enter ranges, compare best and worst case, and measure the steps where the decision depends on the number.

Self-test

1. Where does waiting time come from in the instant calculation?
The instant calculation takes waiting times as input; overload appears as utilization above 100%.
2. What does process mining need?
Mining reconstructs the process from logged events.
3. When is a simulation most useful?
Simulation shows how queues build up when capacity is tight.