Future process: how to evaluate measures

Advanced 11 min read · Updated November 14, 2026

A future process, often called the to-be or target process, is the current process with a set of decided changes applied. Each change is a measure with an owner, a due date, an investment and a concrete effect on the model. Its value is the difference in the metrics with and without it; payback is the investment divided by the monthly saving.

From problem to measure

A measure answers a problem at a step (see finding process weaknesses). To be useful later, it needs more than a sentence. In the app a measure carries:

Effects as changes to the model

The core idea: a measure does not get a guessed saving typed into a field. It changes the model, and the calculation tells you what follows. The possible changes are:

Because effects are model changes, they interact correctly. Removing a query loop changes visits, which changes processing time, cost, utilization and the number of handoffs at once.

Effect and payback

The effect of one measure is the set of metrics with this measure minus the metrics without it, both on the current model. The effect of all enabled measures together is calculated the same way. Each measure can be switched on and off, so you see its own contribution.

The saving per year is the difference in annual cost. Payback is only given when that saving is positive.

Effect = metrics with measure − metrics without measure Payback in months = investment ÷ (saving per year ÷ 12)

Worked example: order number mandatory

In the worked example “Invoice check” (1,000 invoices a month), one invoice in five is incomplete, usually because the order number is missing. Each incomplete invoice goes back to the supplier and waits five working days (2,400 minutes) before it is checked again. The measure “Remind suppliers in writing that the order number is mandatory” costs €3,000 and is expected to halve the share of incomplete invoices from 20% to 10%. In the model this is two changes: the exit “no” of the decision “Complete?” gets 10%, the exit “yes” 90%.

Invoice check, metrics without and with the measure
MetricCurrentWith measureDifference
Lead time per case1,229.5 min895.6 min−333.9 min
Cost per case€17.04€16.53−€0.51
Cost per year (12,000 cases)€204,500€198,389−€6,111
Share without queries or rework80%90%+10 points
Utilization accounts payable101%97.5%−3.5 points

Reading the result

The saving per case is small, only €0.51, because a query costs little processing time: the check is repeated, which is 4 minutes. With 12,000 invoices a year it still adds up to €6,111, so the investment of €3,000 pays back in 3,000 ÷ (6,111 ÷ 12) = 5.9 months.

The larger effect is on lead time: a third of a working day less on average, because fewer invoices wait five days for the supplier. And accounts payable drops from 101% to 97.5% utilization, so the backlog of 10 invoices a month disappears. A measure that looks modest in euros can be the one that makes the process stable. That is why the comparison shows all metrics, not just cost (see process cost calculation and staffing calculation).

Deriving and comparing the future state

When the measures are decided, the app turns the current process with all enabled measures into a separate future process. It has the same lanes and steps with the changed values; removed steps are gone, and the measures stay as documentation, marked as applied, so their effect does not count twice. The current state is kept as the comparison baseline. The future process can then be edited further in the same notation, for example to redraw a step that a new system will take over. The future-state template for incoming invoice processing was created exactly this way from the current one.

The comparison places the current and the future process side by side on the same metrics, with the difference: lead time, processing and waiting time, cost per case and per year, handoffs, media breaks, queries and loops, share without queries, full-time equivalents and highest utilization. That is the basis for a decision paper or a steering meeting.

New processes: plan backwards

Not every future process starts from a current one. For a process that does not exist yet, start at the result and ask “what must have happened before?” until you reach the trigger. Then add volumes and estimated times as for a current process (see volumes and case counts) and check whether the teams have the capacity.

Invoice check (worked example)Invoice check (worked example), drawn from the model the app calculates with, in the same rendering as the export: processing and waiting time per step, “×” top right on steps that run more or less than once per case, the bottleneck step marked in red. The legend below the diagram explains the other symbols. Accounts payable 2 ppl. · 101% Division management 2 ppl. · 84% Supplier Invoice check (worked example) Invoice received ERP Enter invoice 6 min 1 h BOTTLENECK ×1.25 ERP Check invoice 4 min 0 min Complete? Query to supplier 5 working days Amount above €5,000? ×0.3 Approve invoice 5 min 3 working days ERP Post invoice 5 min 2 h Invoice posted yes · 80% no · 20% yes · 30% no · 70% Line width = number of cases Rework loop Bottleneck Lane utilized over 100% Media break worked in an IT system done manually ×0.3 Passes per case, if not exactly one (below 1: only some of the cases) Problem Measure
Invoice check (worked example), drawn from the model the app calculates with, in the same rendering as the export: processing and waiting time per step, “×” top right on steps that run more or less than once per case, the bottleneck step marked in red. The legend below the diagram explains the other symbols.

Try it in the editor

Invoice check (worked example) · 1,000 / month

The worked example contains the problem “one invoice in five is incomplete” and the measure “order number mandatory” with its two changes, so you can switch it on and off.

Open the example in the editor

Free, no sign-up, in your browser. Lead time, cost and utilization are calculated while you draw.

Matching calculator

Process cost calculator: cost per case

Calculate process cost per case and per year: enter steps with processing time, hourly rate and share of cases. Free, same calculation as the editor.

Frequently asked questions

What is the difference between a future process and a measure?

A measure is a single decided change. The future process is the current process with all enabled measures applied, plus any redesign you make on top.

Why is there no payback for some measures?

Payback is only calculated when the annual cost goes down and an investment is entered. A measure that only shortens lead time has a benefit, but no payback in money.

Can measures contradict each other?

They are applied in the order of the markers. If a measure refers to a step that an earlier measure removed, its change is skipped and the checks report it.

How reliable is the saving?

As reliable as the estimates behind it. Enter ranges for times; the lead time is then calculated for best, typical and worst case, which shows how much the result depends on the estimate.

Self-test

1. A measure costs €3,000 and saves €6,111 a year. What is the payback?
3,000 ÷ (6,111 ÷ 12) = 5.9 months.
2. How is the effect of a single measure calculated?
The measure changes the model; the difference in the calculated metrics is its effect.
3. In the example the saving per case is only €0.51. Why is the measure still worth it?
Fewer invoices wait for the supplier, and accounts payable drops below 100% utilization.

Keep learning

Would you like to map or improve a process together with us? Contact